Certifying
- Price / deposit
- Not sold to consumers (operated as a service)
- Certification, as written on the tracker
- FAA type certification in progress. As of July 31, 2026, Joby's shareholder letter showed Stage 4 at 83% company / 77% FAA and Stage 5 at 20% / 10%. On November 4, 2026 Joby said a wide range of "for credit" testing had been completed in stage five. The release does not say stage five is finished. No type certificate is reported as issued.
- Delivery / launch
- Dubai commercial launch targeted for 2026 (six-year exclusive with Dubai RTA); eIPP flights in Texas Sep 2026; Florida eIPP demonstration from St. Petersburg to Tampa on Oct 30 2026. On November 4, 2026 FDOT and GOAA said Joby flew a demonstration at MCO's Vertipad Atlantis, which they call the pad's first use. Those releases do not mention a November 2 date. AvBrief, dated November 8, 2026 and updated November 9, reports a nearly silent Joby demonstration flight at the UP.Summit at Kennedy Space Center. AvBrief does not give the day, does not call it an eIPP flight, and does not say passengers were carried. NASA's November 9 recap does not name Joby. A demonstration is not a type certificate. On November 11, 2026 AIN reported that CFO Rodrigo Brumana placed the initial launch of commercial operations under the eIPP in 2027, while the latest SEC quarterly filing still lists a target of carrying first passengers in 2026. AIN says Joby and Archer previously targeted commercial flights in 2025, and that Joby expects FAA pilots to begin training in the first half of 2027. Those are targets. No type certificate is reported as issued. On November 18, 2026 the Dubai Media Office said GCAA certification of vertiports VMR and VDX enables a route Joby would fly, and that commercial service remains subject to operational approvals and readiness. That is vertiport certification, not a type certificate. The pages do not name the model and do not say a type certificate has been issued. On November 20, 2026 The National reported that Khaled Al Awadhi, director of the RTA's Transportation Systems Department, said testing for the service would start towards the end of this year and that the plan is a commercial passenger launch most probably in Q2 2027, between Dubai Marina and the Dubai International Airport vertiport, with two electric aircraft. The article's lead says trials are set to begin next month. Q2 2027 is a target. Khaleej Times reported on October 15, 2026 that the Dubai launch was targeted for 2026. The November 20 article does not say that 2026 target was withdrawn. It does not say an air operator certificate or a type certificate has been issued.
- Tracker updated
Certificates
A special or experimental airworthiness certificate, a production approval and an operator certificate are not type certificates. Standing is taken from the linked source.
No certification row is recorded here yet.
Orders and other deals
No funding or order row is recorded here yet.
Milestones
| Date | Vehicle | Kind | Event | Sources |
|---|---|---|---|---|
Slipped date |
RTA official puts a Dubai passenger launch most probably in Q2 2027The National reported on November 20, 2026 that Khaled Al Awadhi of Dubai's RTA said the plan is a commercial passenger launch most probably in the second quarter of 2027. That quarter is a target. Khaleej Times reported on October 15, 2026 that the launch was targeted for 2026. The November 20 article does not say the 2026 target was withdrawn. No type certificate or air operator certificate is stated as issued. Two aircraft at the start is not described as a firm order. |
|||
Infrastructure |
Dubai Marina Vertiport VMR certified; commercial service not startedThe Dubai Media Office said on November 18, 2026 that the GCAA certified the Dubai Marina Vertiport, call sign VMR, under CAR AGA Part VFI, and that VDX was already certified under that regulation. It says the certification enables a route Joby would fly, and that commercial service remains subject to operational approvals and readiness. A vertiport certificate is not an aircraft type certificate. The pages do not name the model and do not say a type certificate has been issued. The National reports the same limit on the start of service. |
|||
Slipped date |
AIN reports a 2027 target for Joby's initial eIPP commercial launchAviation International News reported on November 11, 2026 that CFO Rodrigo Brumana placed Joby's initial launch of commercial operations under the eIPP in 2027. AIN says Joby and Archer previously targeted commercial flights in 2025. AIN reports that Joby's latest SEC quarterly filing still lists a target of carrying first passengers in 2026, and that Joby expects FAA pilots to begin training on its aircraft in the first half of 2027. Those are targets. The 2026 filing target is not described as withdrawn. No type certificate is reported as issued. This is a timeline note, not a status upgrade. |
|||
Other |
AvBrief reports a Joby demonstration at the UP.SummitAvBrief, dated November 8, 2026 and updated November 9, reports a nearly silent demonstration flight by Joby at the UP.Summit, which AvBrief says NASA hosted for the first time at Kennedy Space Center. AvBrief does not give the day, does not name a registration, does not call the flight an eIPP operation, and does not say passengers were carried. NASA's November 9 recap of MAX POWER says UP.Summit events ran November 4 to 8 and does not name Joby. A demonstration is not a type certificate. This is not a statement that Joby's October 30 plan for a Kennedy stop was completed. |
|||
Piloted flight |
Joby demonstration at Orlando's Vertipad AtlantisFDOT and the Greater Orlando Aviation Authority said on November 4, 2026 that Joby flew a demonstration that day at Vertipad Atlantis, and both called it the pad's first use. FDOT says Joby piloted the flight. Both call the site the first of its kind at a commercial airport. That wording is their claim. GOAA says the pad is laying the groundwork for a future vertiport for commercial operations. No type certificate is reported. The releases do not mention a November 2 date. The photograph GOAA published shows registration N545JX, which AIN had identified as Joby's conforming prototype on the Tampa Bay flight. A conforming prototype is not a type certificate. |
|||
Certification step |
Joby reports for-credit testing in stage fiveJoby said on November 4, 2026 that a wide range of "for credit" testing had been completed in stage five, which it calls the fifth and final stage of FAA type certification. The release does not say stage five is finished, and it does not give a new percentage. It does not say a type certificate has been issued. The July 31, 2026 shareholder letter remains the last published stage split: stage 4 at 83 percent company / 77 percent FAA, and stage 5 at 20 percent / 10 percent. Joby also says 17 aircraft are in production, third-quarter revenue was $55 million primarily from Blade, cash and short-term investments were $2.2 billion at September 30, and the 2026 revenue outlook is $135 million to $140 million. A Resonant Sciences acquisition is described as planned, with closing conditions still named. That is not a completed acquisition. |
|||
Piloted flight |
Florida eIPP demonstration from St. Petersburg to TampaThe FAA said on October 30, 2026 that Joby's S4 and BETA's ALIA CX300 flew from Albert Whitted Airport in St. Petersburg to Tampa, in Florida's first eIPP demonstrations. AIN reports Joby's aircraft as conforming prototype N545JX, taking off about 10 a.m. and landing about 20 minutes later. Flying Magazine, citing FlightAware, reports a 10:01 a.m. EDT departure and a landing on Runway 1R. A conforming prototype is not a type certificate. On November 4, 2026 FDOT and GOAA reported a Joby demonstration at Vertipad Atlantis. Those releases do not mention a November 2 date. A later AvBrief report of a Joby demonstration at the UP.Summit at Kennedy Space Center is a separate milestone. AvBrief does not call that flight an eIPP operation or give the day. NASA's November 9 recap does not name Joby. |
|||
Infrastructure |
Dubai International Airport vertiport technically completeSkyports and the RTA said the flagship vertiport was technically complete and ready for eVTOL aircraft. Passenger service had not started. No opening date was stated in that announcement. |
|||
Piloted flight |
Piloted test flights in DubaiSkyports said Joby completed piloted test flights in Margham in June 2025, including the first UAE piloted flights between two places, Margham and Al Maktoum International Airport. Skyports did not give the day. |
Slipped timeline
- Launch of commercial flights in 2025, which Aviation International News says Joby and Archer previously targeted. Joby's latest SEC quarterly filing still lists a target of carrying first passengers in 2026. AIN reported on November 11, 2026 that CFO Rodrigo Brumana placed the initial launch of commercial operations under the eIPP in 2027. AIN also reports that the filing still lists a 2026 target for first passengers, and that Joby expects FAA pilots to begin training on its aircraft in the first half of 2027. 2025, 2026 and 2027 are targets. The 2026 filing target is not described as withdrawn. No type certificate is reported as issued. Aviation International News, Nov 11 2026
- Commercial launch targeted for 2026, which Khaleej Times reported on October 15, 2026, under a February 2024 agreement that gives Joby exclusive rights in Dubai for six years. The National reported on November 20, 2026 that Khaled Al Awadhi, director of the RTA's Transportation Systems Department, said the plan is a commercial passenger launch most probably in Q2 2027, with testing towards the end of this year. The article's lead says trials begin next month. Those are targets. The November 20 article does not say the 2026 target was withdrawn. It does not say an air operator certificate or a type certificate has been issued. The November 18 pages still say commercial service remains subject to operational approvals and readiness. The November 20 article does not repeat that sentence and does not say the condition was lifted. Khaleej Times, Oct 15 2026
The National, Nov 20 2026
Dubai Media Office, Nov 18 2026
Video
Joby Aviation Flies in Dubai
Piloted, full-transition flights in Dubai, June 2025. Video and poster: Joby Aviation · Watch on YouTubeGOAA VNR - Joby Demo Flight
The Greater Orlando Aviation Authority's November 4, 2026 release links this video as the video of the initial eVTOL flight at Orlando International Airport, hosted by FDOT. YouTube lists the publish date as Nov 4, 2026. Video and poster: Greater Orlando Aviation Authority · Watch on YouTubeTracker sources
- Joby Q2 2026 shareholder letter (SEC)
- Khaleej Times, Oct 15 2026
- Joby, Sep 10 2026
- FAA, Oct 30 2026
- Joby, Oct 30 2026
- Aviation International News, Oct 31 2026
- FDOT, Nov 4 2026
- Greater Orlando Aviation Authority, Nov 4 2026
- Joby Q3 2026 results, Nov 4 2026
- Aviation International News, Nov 11 2026
- AvBrief, Nov 8 2026
- NASA, Nov 9 2026
- Dubai Media Office, Nov 18 2026
- The National, publish time Nov 19 2026
- The National, Nov 20 2026